Friday, October 2, 2009

Ground Breaking Ceremony - September 30, 2009


A ground breaking ceremony was held on September 30 for the Hot Sulphur Springs Water Project. It was attended by members of the community, town board members, town staff, people who have helped on this project and by employees of Garney Companies, Inc, the general contractor.

It is an important step forward for Hot Sulphur Springs water quality and quantity. The time frame from the project conception, through engineering, approval and bid award processes was swift and was accomplished by the hard work of many people, especially the town board and staff.

The people in this photograph are Geoff Elliott from Grand Environmental Services, Program Manager & Owner's Representative; Curt Thompson from Merrick & Company, Project Manager/Engineer; Hershal Deputy, Hot Sulphur Springs Mayor; Matt Sugar, Regional Representative for Senator Mark Udall; Andy Poirot, District Engineer from the Colorado Department of Public Health and Environment; and Ed Duerr from Ed Duerr, Inc., Assistant Project Manager/Engineer.

For a copy of a newspaper article from the Sky Hi News on October 1, please click on this link.

Wednesday, September 16, 2009

Groundbreaking Ceremony - 10 a.m. Wed, Sept. 30

There will be a groundbreaking ceremony for the Hot Sulphur Springs Water Projects at 10 a.m. on Wednesday, September 30 at the Hot Sulphur Springs Water Treatment Plant. Everyone is invited!

Friday, August 7, 2009

Invitation to Bid Announcement

An Invitation to Bid is being advertised in the MP Times and Sky Hi Daily News on August 6, 7, 13 and 14. The announcement gives information about the bid process and encourages local contractors and subcontractors to form teams to successfully bid for the project and to attend a mandatory pre-bid meeting on August 18 at the Hot Sulphur Springs Town Hall at 10 a.m. Bids will be due on September 3.

Beginning August 12, project plans and specifications may be reviewed or purchased for $100 at the Hot Sulphur Springs Town Hall or at the Merrick and Company offices in Aurora.

A Project Summary is available online. Be sure to check the construction page of this website for construction and contracting information.

Wednesday, July 15, 2009

Colorado River Clearing Up!



Water in the river is improving after the upstream events from last week. Turbidity is still elevated but within normal range for runoff and the water treatment plant is fully operational again. Ecological sampling yesterday revealed many bugs still healthy in the river including stoneflies, caddis, mayflies, boatmen, and water striders. Some folks are even catching fish again.

This sediment problem could have been much worse and operator Jim Kleeman and clerk Sandy White did a great job of keeping water flowing to town residents. The whole situation underlines our need for new water intake, filter, clear well, and storage tank.

Monday, July 13, 2009

Watering Restrictions Return to Normal

Watering Restrictions Back to Even-Odd Days

The Town of Hot Sulphur Springs water treatment plant is back to normal production again, as of Monday 13July09 in the morning, thanks to improved sediment loads in the river. Town residents can now return to their normal (even-odd day) watering schedules. A no-outside-watering restriction was put in place via a “reverse-911” emergency call on Wednesday July 8, 2009 due to an upstream sediment spill into the Colorado River which drove river water turbidity to levels 60 times higher than typical runoff quality.

For more information call Town Hall at 970-725-3933. Thank you for your cooperation.

Friday, July 10, 2009

Water System Up and Running, with a Little Bit of Help from our Neighbors


Operator Jim Kleeman got the Town Water Treatment Plant going with one filter yesterday (Thursday) morning as sediment loads dropped in the river below 50 NTUs (turbidity units). Raw water quality improved throughout the day and we are optimistic things will continue to get better. We are not out of the woods yet so we are still getting deliveries of clean potable water from Granby and Steamboat to keep the tank level up. The photo above is of 2,000 gallon tank truck from Raindrop Water of Steamboat Springs.

Thursday, July 9, 2009

Sediment Problem 7-9-09


An incident upstream sent tons of sediment down the Colorado River late Tuesday (7/7/09), overwhelming the Hot Sulphur springs water system and temporarily shutting it down. Turbidity was 60 times worse than the murkiest spring runoff conditions, but improved considerably by the next day. On Wednesday, water trucks arrived with potable water from Granby to keep the water system going. Hopefully, the water plant will be up and running today (Thursday). Thank you to everyone who respected the emergency watering restrictions!

It is a good thing that construction on the new water system is in the works! When the new ARRA system is in place, Hot Sulphur Springs could shut down the water plant for 2 or more days and still have dependable water in the two tanks.

Friday, July 3, 2009

100% Plans are Submitted to Colorado Department of Public Health & Environment


We met our deadline to submit a completed application with detailed drawings and design specifications and Environmental Assessment to the Colorado Department of Public Health and Environment (CDPHE). This completed an 8-week whirlwind effort including public meetings, site mapping and surveys, numerous engineering meetings and many hours from our dedicated team of engineers, surveyors, town and environmental planners, attorneys, and staff. Our submittal was made to CDPHE early, of course, with a comfortable 40 minutes to spare before the drop-dead deadline. We were working up to the 11th hour on peripheral issues such as floodplain mapping and plumbing details. Thank you team for a job well done!

Our ARRA stimulus project immediately triggered work in Grand County and Denver:


Hot Sulphur Springs Stimulus Project Generating Local Work:

  • Town of Hot Sulphur Springs – hired new water-treatment-plant operator to support new construction efforts.
  • Tim Shenk Land Surveying of Granby – surveying water treatment plant site and water tank site, also FEMA 100-year-floodplain studies.
  • Merrick Engineers of Aurora – design and engineering for water treatment plant (new membrane filter and replace clear well) and new water tank.
  • Conservation Assistance of Grand Lake – public involvement and editing/production for environmental assessment.
  • Ed Moyer of Hot Sulphur Springs – Contract town planner coordination land use and town and county masterplans.
  • TopKnot Engineering of Hot Sulphur Springs – Engineering design for water intake structure, guidance on town utilities.
  • Grand County Title and Escrow – Property ownership patterns and title commitments.
  • Kumar and Associates of Fraser – Geotechnical investigation of water tank site.
  • Paper Clip of Granby – Office supplies, report production, and secretarial support for project management.
  • Frye Business Services and Systems of Fraser – Project organization and accounting, upgrades for computer systems in Town Hall to support capital projects.
  • County Seat Restaurant – Lunch meetings for planning team.
  • Java Lava – Coffee, breakfast, and lunch for planning team.
  • Grand Environmental Services – Project management, communications, environmental assessment, wetland delineation and permitting in waters of the US.

Monday, June 8, 2009

Initial Project Scoping Letter


The following letter was distributed to agency officials, neighbors, and other concerned parties to define the initial project scope.

Click Here to See the Letter

Click Here to See Figure 1 - Project Location

Click Here to See Figure 2 - Proposed Action Locations

Tuesday, June 2, 2009

Welcome to the HSS Drinking Water Recovery Project Blog

Welcome to the current news and announcements for the Hot Sulphur Springs Drinking Water Recovery Project. We will post announcements and links to updated documents, drawings, and other related information on this page.